Bridge Installation

Here is a run-down of the installation of the first bridge.


Crane 1 is positioned on the riverbank near the 14th forward tees.

Crane 2, and the bridge, are positioned on the opposite bank,
near the 10th green.

The bridge is hoisted into position, by crane 2, and placed on top of
a barge situated in the river.

A line is attached to the truck on the far bank, and a winch
on the truck begins pulling the bridge, and barge, across the gap.

The bridge is pulled across the gap.

Finally, cranes 1 and 2 pick up the bridge, the barge is pulled out of the way
and set into position. A very exciting day at
Cape Arundel to say the least!
All of us on the maintenance staff would like to thank
everyone who made this possible.
Brendan