The work on the golf course improvements is 95% complete. All rebuilt tees have been sodded, and all new bunkers have been built, drained, and sodded. The remaining work includes the bunker at the 10th green, which needs new drainage and the right, 13th greenside bunker that needs new sand. All main drain lines have been installed, and there is about 2,000 feet of lateral drain pipe left to be installed. Please enjoy the photos.